Journal The build process
Building in McAllen While You Live in Mexico: What You See Each Week
Every week you get photos and a message from the job. This is what those photos show at each stage of a Sisu build, and which decisions stay with you.

- By
- Daniel Estrada Founder and general contractor
- Published
- , 5 min read
- Topic
- The build process
If you live in Mexico, or anywhere far from the Valley, one question sits under all the others: how you will know what is happening on your lot.
At Sisu the answer comes every week. You get photos and a message from the job, and you can follow the project online from wherever you are. Below is what those photos show at each stage, in the order the work happens, and the decisions that come to you.
Who runs the job while I am away?
Sisu takes your project from the design and the permits to the finished building, then helps you sell it or rent it. You work with one company, in English or Spanish.
Daniel Estrada, our founder, is the general contractor on every job. He is on every jobsite every week and at every framing inspection. Sisu is insured, with builder's risk on every build.
How do I follow the build from Mexico?
Every week you get photos and a message on where the project stands. You can also follow the project online from wherever you are.
If a photo leaves you with a question, write to Daniel on WhatsApp at (956) 414 8777. When you are in town, come walk the site with him.
What will I see before construction starts?
For one home, the lot, the design and the permits take 1 to 2 months. Most of what you see in these weeks is on paper: the drawings, the price and the city paperwork.
The first call. Twenty minutes with Daniel. You tell him what you want to build and whether you plan to sell or rent. He tells you plainly what it takes.
The lot. We check zoning, easements, utilities, drainage and soil on the lot you have or the one you are looking at. The soils report tells us what the slab needs, and you get it in writing. Your decision here is the lot itself, made before you buy it.
The design. We draw the project with you room by room and show it to you in 3D before anything is final. You decide the rooms, the layout and the exterior. Design moves as fast as those decisions do.
The price and the contract. You get a written price, line by line, before you sign. The finishes you pick from our design range are priced in it, and the price on the signed contract holds through the build.
The permits. We pull the permit with the city or county that has your lot. While it reviews the drawings, you close the construction loan, so work can start the day the permit is issued. Your decisions in this stretch are the lender and the loan closing.
A project with several units has its own schedule. Daniel goes over it with you on a call.
What do the weekly photos show once the build starts?
Construction takes 6 to 10 months from contract to keys, depending on the size of the home. The work goes in a fixed order, and every stage passes inspection before the next crew starts. The photos follow that same order.
The slab. The slab is engineered to the soils report for your lot. The first photos show the beams dug, the plumbing laid in under the slab and the steel sitting on chairs over a vapor barrier. After the foundation inspection, the concrete goes in over the steel and the crew screeds and floats it flat.
Framing and the roof. The crew raises the walls on the slab, then the floor and roof trusses. Daniel is at every framing inspection. Then the roof goes on, the windows and doors are set, and the house is dried in. Rain matters most before this point. After it, most of the work keeps going.
Framing is also when the size of the rooms first shows in the photos. If you want to move an outlet or shift a wall, mark it on the plan and talk to Daniel before anyone touches it. A change on a framed wall costs more than it looks like it will.
Inside the walls. Plumbing, wiring and air conditioning run through the walls and ceilings, and each passes inspection before the walls close. Licensed trades do the electrical, plumbing and air conditioning. Then the insulation goes in. These are the last photos that show the house as wood and wire.
Drywall, finishes and the outside. Drywall closes the walls and the rooms take their shape. Then come cabinets, counters, tile, trim and paint, in the colors you picked by the dates on your selection schedule. Outside, the walls get the finish the plan calls for: stucco, brick, stone or siding.
The keys. After the final inspection, the city or county issues the Certificate of Occupancy. You walk the house with Daniel and get the keys, with a written warranty: 1 year workmanship, 2 years systems, 6 years structural.
Which decisions are mine during the build?
Once the slab is poured, most of your decisions are finishes. Tile, fixtures and colors each have a date on the selection schedule. A late pick means a late order, and a late order means a crew waiting on site. If you already know the tile or the fixture you want, pick it during design so it gets ordered on time.
Change orders come only from you. If a photo makes you want something different, tell Daniel, and the change starts with your request.
Our process page lays out each step with what you decide and what you get in writing. For the month by month view, read how long it takes to build a custom home in McAllen.
What happens when the building is finished?
The keys come with the written warranty, backed by Sisu. Then we help you sell it or rent it, so the same company stays with you from the first call to the sale or the rental.
Frequently asked questions
Do I have to be in McAllen during the build?
You do not have to be in the Valley while we build. Every week you get photos and a message from the job, and when you are in town you can walk the site with Daniel.
Can I follow the project online?
Yes, from wherever you are, along with the weekly photos and message.
How long does a build take?
For one home, design and permits take 1 to 2 months, and construction takes 6 to 10 months from contract to keys, depending on its size. A project with several units has its own schedule.
Can we work in Spanish?
Yes. Calls, messages and updates go in English or Spanish, whichever you prefer. Call or write on WhatsApp at (956) 414 8777.
See how Sisu works with investors on our investor page, then book a 20 minute call with Daniel and tell him what you want to build and where you are writing from.